SCJ: You Snooze You Lose: Tower Restoration v. Attorney General of Canada, 2021 ONSC 3063 (CanLII)
Background.
Agreements between two sophisticated parties are generally
looked at a different light by the courts. A court is likely to adopt a textual
interpretation of the agreement. This contrasted to how legislation is
generally interpreted nowadays, where a purposive interpretation is taken by
the courts.
In this recent case, the Government of Canada accepted a bid
from a proponent (“Tower”) for the replacement of all the windows of a federal
penitentiary.
Tower was given a lump sum by Canada to complete the project.
Tower incurred further charges that it sought to obtain from
Canada. Tower submitted a “claim” under the governing agreement between the
parties. Canada rejected the claim and issued a final decision. Tower
acknowledged receipt of the decision.
The terms of the dispute resolution clause required Tower to
dispute the decision within 15 day of the decision. However, Tower failed to do
so.
It now brings an action of which Canada brought a summary
judgment to dismiss the case altogether.
Court.
The court decided that there were no material facts in
dispute and there was no genuine issue for trial.
The court rejected Tower’s argument that there was an
implied waiver to the dispute resolution deadline to challenge a final
decision. The court reasoned that Tower’s evidence does not support such an
implied waiver.
The court held that Canada adhered strictly to the terms of
the agreement throughout the duration of the contract. It never once paid Tower
outside of the strict processes contemplated in the GC, which included
provisions related to dispute resolution in the event of disagreement.
There was no air of reality to Tower’s waiver argument, the
court held. The court reasoned:
[22] There is simply no air of reality to
Tower’s waiver argument. Tower was a sophisticated commercial enterprise
engaged in a multi-million-dollar contract with the Government. It knew that it
would have to comply with the strict terms of the GC to receive additional
payment totalling over $1,000,000. Most tellingly, Tower employed the process
outlined in the GC to make the 2013 Claim in the first instance.
The court then went to stating that when Tower failed to
provide notice of the dispute to Canada, it accepted Canada’s final decision.
The court justified the importance of binding notice provisions in a contract
through policy rationales. Holding that the purpose of binding notice
provisions is to provide the other party with sufficiently detailed information
to allow it to consider its options and take corrective action before the
contractor pursues a claim.
Noting that such policies is important in disputes in government
construction contracts, which involve sophisticated commercial enterprises, a
competitive bidding and selection process, use of public funds, contracts of
adhesion, and which have precedential value beyond the immediate parties: Ledcor
Construction Ltd. v. Northbridge Indemnity Insurance Co., [2016] SCC 37 at
para. 37-43.
Takeaway.
The courts place a high standard on sophisticated commercial
parties to follow the contract with precision. With good reason, contracts such
as the one in this case must have taken months or even years to create. For a
court to start setting aside displaces first contract law principles such as consensus
ad idem and the many other principles that govern our contract law. Not to
mention the time and energy invested to govern the parties.
Comments
Post a Comment